Production Update. DVT#2 Has Begun

OK Jamie
good night :sleeping:

1 Like

The same procedure as every time, one is already a bit used to it, but of course it is not really nice.

Das gleiche Vorgehen wie jedesmal, man ist inzwischen schon ein bisschen daran gewöhnt, aber wirklich schön ist es natürlich nicht.

2 Likes

Hi Jamie,
do you already have any more updated details for us patiently waiting Carbonizers?

Now I am a little disappointed. Today I will not wait that long. :disappointed:

hello all,
we are preparing the video update for October.
It should be out tonight. :wink:

2 Likes

Hi all
New post here.
I will be sharing some content on the relevant groups for aspects such as packaging and the case for discussion.
Thank you for your patience on this.
Jamie

1 Like

Good morning everyone,
did I miss any news or presentation last night?
Are there any news about delivery?
Is there any progress?

Morning Stephan.
See my post above yours :slight_smile:
Thanks
Jamie

1 Like

The packaging makes a very good visual impression. I am very curious to see how it looks inside.
And the video sequence is really very impressive. :+1:
Many greetings and a great weekend.
Bernd

Are there any plans to update the processor? On my opinion the processor is now much more older then one year…
and the Carbon I is still not for sale.

2 Likes

Ich denke das wird nicht möglich sein, wenn wir es noch vor Ostern haben wollen. Andererseits, das Weihnachtsgeschäft ist jetzt eh schon durch. :grin:

2 Likes

Hello, I was asking nearly the same, but it doesn’t seem to be that easy. Here‘s the answer I got from Firas: What's Next? Tell us your ideas

Good evening Carbon team, do you have any updates, news, infos or just some nice pics for us?

1 Like

@jamie
grafik
Since Thursday finished: Antenna & Mainboard Production, until tomorrow finished: DTV#2 Assembly.
Could you keep the timeline up to here?

1 Like

Status Update: 16-11-2020

Hello all,

We are got all issues resolved, getting ready for DVT#2.

We have to push back DVT#2 date after quality check requirements on some of the parts.
Meaning we are doing an assembly for a smaller quantity before the big DVT#2 assembly.
Pending parts so far:

  • Antenna: delivery tomorrow.
  • Mainboard: delivery Wednesday.
  • Speaker box: there was some tuning required, we made an adjustment last week, and parts re-worked to arrive this week again. Arriving this week.

All other parts are ready, and software is fully integrated for the latest hardware/camera tunning changes.

We had to push DVT#2, to early next week.

We already prepared units for testing and certification, trying to maintain time and quality control.

Will keep you posted with the latest news.
Unfortunately, the team is super hooked and can’t take photos. We should be able to share more next week.

Best,
Firas.

4 Likes

Quiet, silence… are there any news, updates? We are looking forward for some final news about production and upcoming delivery status.
Good morning Berlin😊

Stephan, just coming online to update :slight_smile:

Latest news from the Carbon Development Team.

We have seen big progress with all parts received now for assembly with the exception of the mainboards which are due tomorrow morning.
We needed to do a last-minute tuning and test each individual mainboard for a full functionality test.

Development Validation Testing #2 (DVT#2) is now planned for Saturday to Monday, with all parts ready for the first 80 devices to be put into production and testing.

While doing all of the above, we are trying to save time on certification.
We started the pre-testing process for CE and GMS (Google Certification).
So another milestone here is we passed the pre-testing for these 2 certifications.

We will be sharing more photos from the assembly of the DVT#2 on Monday/Tuesday with a full video update.

Looking forward to showing you 80 beautiful, powered up devices on the production line!

3 Likes

Nicht mehr lange dann bekommen wir unsere Handys :grin:

1 Like

Oh very nice! Progress sounds so gooood👍🏼

Very exciting… can’t wait.